IEQ Credit 8.1: Daylight
LEED Credit: 1 point
Intent:
Provide building occupants with a connection between indoor spaces and the
outdoors through the introduction of daylight and views into the occupied areas
of the building.
Requirements*
Through 1 of the 4 options, achieve daylighting in at least the following
spaces:
* Exceptions for areas where tasks would be hindered by the use of daylight.
OPTION 1: Simulation
Demonstrate through computer simulations that 75% or more of all regularly
occupied spaces areas achieve daylight illuminance levels of a minimum of 25
footcandles (fc) and a maximum of 500 fc in a clear sky condition on September
21 at 9 a.m. and 3 p.m. Areas with illuminance levels below or above the range
do not comply. However, designs that incorporate view-preserving automated
shades for glare control may demonstrate compliance for only the minimum 25 fc
illuminance level.
OPTION 2: Prescriptive
Use a combination of side-lighting and/or top-lighting to achieve a total
daylighting zone that is at least 75% of all the regularly occupied spaces.
OPTION 3: Measurement
Demonstrate through records of indoor light measurements that a minimum daylight
illumination level of 25 fc has been achieved in at least 75% of all regularly
occupied areas. Measurements must be taken on a 10-foot grid for all occupied
spaces and recorded on building floor plans.
Only the square footage associated with the portions of rooms or spaces meeting
the minimum illumination requirements may be counted in the calculations.
OPTION 4: Combination
Any of the above calculation methods may be combined to document the minimum
daylight illumination in at least 75% of all regularly occupied spaces. The
different methods used in each space must be clearly recorded on all building
plans.
IEQ Credit 8.2: Views
LEED Credit: 1 point
Intent:
Provide building occupants a connection to the outdoors through the introduction
of daylight and views into the regularly occupied areas of the building.
Requirements
Achieve direct line of sight to vision glazing between 30” and 90” above the
finish floor for building occupants in 90% of all regularly occupied spaces.
For private offices, the entire square footage of the office may be counted if
75% or more of the area has a direct line of sight to perimeter vision glazing.
For multi-occupant spaces, the actual square footage with a direct line of sight
to perimeter vision glazing is counted.
|
JEB Contribution: |
|
JE
Berkowitz efficiently fabricates high
performance and spectrally selective* glass products from regional
and global manufacturers including
PPG, Guardian and Pilkington to help maximize natural light into the building
while providing excellent solar control in compliance with ASHRE 90.1.
*Glass achieving a Light-to-Solar Gain (LSG) of more than 1.25 as defined by the
U.S. Department of Energy (DOE). |